Sign 1: Progress Claims Arriving Early

A builder who submits progress claims early, or claims amounts above the

contractual milestones, is often managing cashflow difficulties or

over-claiming. Review every progress claim against the actual work

completed before authorising payment. Overpayments are almost impossible

to recover if the builder encounters financial difficulty.

Sign 2: Increasing Number of Variations

A small number of variations is normal. A large and growing number of

variations — particularly for items that should have been in the

original contract — suggests the builder tendered at an

unrealistically low price and is recovering margin through the variation

process. Review each variation carefully against the contract

documentation.

Sign 3: Trades Disappearing From Site

If your site is regularly empty, or trades stop appearing without

explanation, the builder may be diverting labour to other projects or

experiencing subcontractor payment disputes. A healthy project has

continuous activity on site through the construction phase.

Sign 4: Programme Slipping

If programme milestones are consistently being missed — even by small

amounts — the cumulative effect will be significant. A builder who is

2 weeks behind on each of the first 5 milestones is likely to finish

4–6 months late. Address programme slippage early and formally, in

writing.

Sign 5: Requests for Information (RFIs) Ignored or Delayed

Builders use RFIs to seek clarification on the design. A high volume of

RFIs is a sign of documentation quality issues. RFIs that go unanswered

by the design team are a sign of poor project management. Either way,

unanswered RFIs slow construction and give the builder legitimate

grounds for delay and variation claims.

Signs 6–10

Sign 6: Subcontractors telling you about payment issues — contractors

talk to owners when the head contractor isn’t paying them. Sign 7:

Quality of work declining mid-project — often a sign of financial

pressure and corner-cutting. Sign 8: Builder becoming less communicative

— hard to reach, slow to respond, avoiding site meetings. Sign 9:

Unexplained material substitutions — different products to those

specified being installed without formal variation approval. Sign 10:

Work failing inspections — building surveyor raising non-compliance

issues that the builder is slow to rectify.

What to Do If You See These Signs

First, document everything — all communications in writing, all

progress claims reviewed and annotated. Second, obtain professional

advice from an architect or construction lawyer before the situation

escalates further. Third, consider engaging Integral Design Solutions as

a project manager or project advocate if you are not already using one.

We have substantial experience in taking over struggling projects and

bringing them back on track.

Ready to Get Started? Contact Integral Design Solutions today for

expert construction project management and dispute resolution services

in Melbourne and Victoria. Visit integraldesignsolutions.com.au/ or

call us to book a free consultation.

Info@integraldesignsolutions.com.au

208 White Road, North Wonthaggi VIC 3995, Australia

cropped-IDS.png

A profound design process eventually makes the patron, the architect, and every occasional process eventually makes the patron

copyright 2026 integraldesignsolutions